Tag Archives: Yasen

Bulava Success

Interfaks and ITAR-TASS report Borey-class SSBN Yuriy Dolgorukiy successfully launched its third Bulava SLBM today, that’s the 17th overall test and the 10th success (including five in a row).

The earlier-reported launch window was missed due to bad weather, according to Flotprom.ru.

ITAR-TASS quoted the VPK this week regarding Borey unit 2 Aleksandr Nevskiy.  The VPK says Nevskiy won’t fire a Bulava before the summer of 2012.  After finishing its factory underway testing (ZKhI or ЗХИ) and several successful single Bulava launches, Nevskiy might be accepted into service by the end of 2012, according to the VPK.

Nevskiy’s now on a two-week phase of ZKhI and will be back in Severodvinsk by early December to rectify any problems identified.  ITAR-TASS says underway testing will continue as the weather permits.

Rossiyskaya gazeta Wednesday also noted that Nevskiy’s schedule has moved to the right, and it can’t be accepted until 2012.  RG covered how the first two Boreys used unused proyekt 971 Akula components, but some are talking about Borey unit three Vladimir Monomakh as a “modernized variant” and its builders will no longer be forced to stuff their “new contents” into a “different” hull.  Others have cited the lack of leftover parts as a problem that will increase the cost and difficulty of building the third new SSBN.

The paper says Nevskiy’s crew trained at Obninsk, and also aboard Dolgorukiy.  Like Dolgorukiy, Nevskiy will head for the Pacific Fleet, according to RG.  OSK and the Defense Ministry remain in difficult negotiations over the Borey’s reported 23-billion-ruble price tag.

Updating a related story, ITAR-TASS says new Yasen-class SSN Severodvinsk is now in its second underway period.  Its first (September until early October) was deemed successful; 80 percent of tasks were completed and only minor problems identified.

Worth recalling here that two Boreys, Bulava, and one Yasen were all on President Medvedev’s list of weapons systems to be procured in GOZ-2010.

Difficult Course to a Grand Fleet

Konstantin Bogdanov sees reason for pessimism when looking at the course ahead for rebuilding Russia’s fleet.  Writing in Friday’s Nezavisimoye voyennoye obozreniye, he says, despite an intention to spend 4.7 trillion rubles of the ten-year GPV on the Navy, there are technical challenges, clearly impractical schemes, and failures in what he calls the “organization-financial plan” ahead. 

Bogdanov provides us a handy review of the state of Russian shipbuilding.

He points first to OSK’s insistence on seeing new aircraft carriers (with nuclear-powered destroyers in their battle groups) on the Russian Navy’s horizon.  But Defense Minister Serdyukov has only a cold rebuff for the idea.  Early R&D into what a new carrier might look like is as far as he’s being willing to go.  It was made pretty clear that a carrier isn’t part of this GPV.

Bogdanov says OSK may be looking for work for the New-Admiralty Wharves it sees on Kotlin Island in the future.  The 30- to 60-billion-ruble shipyard could be ready in 2016.  An aircraft carrier project would help launch this idea.

Then Bogdanov turns to the Navy’s more immediate needs — frigates and corvettes.  

Proyekt 22350 frigates are needed by tens, if not 30, or even 40, of them.  But Northern Wharf is having trouble building them.  Lead unit Admiral of the Fleet of the Soviet Union Gorshkov was five years in construction, and its underway testing isn’t complete.  Fleet Admiral Kasatonov was laid down just about two years ago.  Its SAM system, Poliment-Redut with 9M96 missiles isn’t ready, and will have to be fitted right to finished frigates.  But Bogdanov sees the frigates’ VLS – the Multipurpose Ship Fire System (UKSK or УКСК) as a positive step.  It could fire antiship, antisubmarine, land-attack cruise missiles, torpedoes, and possibly SAMs.

When proyekt 22350 didn’t come along quickly, Bogdanov says, the Navy went for its own proyekt 11356M frigates like those being built for India.  But, he notes, Baltic Shipbuilding Plant “Yantar” in Kaliningrad isn’t having an easy time constructing them for its Indian and Russian customers.  There are delays in the Indian units, but Admiral Grigorovich and Admiral Essen have been laid down for Russia, and Admiral Makarov should join them soon.  The contract for a second batch of three was just signed.  They’re supposed to be “localized,” but may actually be more like the Indian versions.  They’re slightly cheaper than the proyekt 22350 at 10 billion vs. 16 billion rubles per ship.

Northern Wharf has the order for nine proyekt 20380 Steregushchiy-class corvettes (with the proyekt 22350 frigates this comes to more than 220 billion rubles).  Soobrazitelnyy (proyekt 20381) began sea trials this year, Boykiy was launched, Stoykiy is under construction, and Provornyy (proyekt 20385) was laid down.  Sovershennyy (proyekt 20380) remains under construction at Komsomolsk-na-Amure.  Bogdanov says the proyekt 20385 ships will have an eight-cell UKSK.

Bogdanov notes, however, that Northern Wharf’s production won’t be steady until its ownership issue is finally resolved.  If OSK takes over, this could have a good or bad effect on fulfilling defense orders, but the current financial questions around Northern Wharf are even worse.

Turning to submarines, Bogdanov believes the situation is more transparent, but there are still questions.

The SSBN picture is pretty clear.  Proyekt 955 Borey-class SSBNs finally have a missile that looks like it works.  Yuriy Dolgorukiy has fired it, and Aleksandr Nevskiy might this year.  Vladimir Monomakh is under construction, and they’re preparing production materials for Saint Nikolay.

The problem, he notes, is units 1 and 2 used sections and components of proyekt 971 and 949A submarines never built.  Units 3 and 4 will be built from scratch, and it’s too early to say how this will be reflected in their cost.  Bogdanov concludes another battle over inflated prices awaits, and there is, of course, still no 2011 contract with Sevmash.

It’s less clear with the multipurpose proyekt 885, Yasen-class, of which the Navy wants ten by 2020.  But these boats have been the focus of the Defense Ministry’s familiar complaint about unjustified price increases.  Unit 1 Severodvinsk was built from materials and resources on hand, and its rising price was frozen at 47 billion rubles in 2005.  The Defense Ministry says Sevmash wants 112 billion for unit 2 Kazan

Bogdanov thinks it’s hard to tell who’s justified here.  There is structural industrial inflation, and a higher costs could be the result of the frozen handover price on Severodvinsk.

Bogdanov mentions the thought given to cheaper attack boats like the Victor III or Akula, or proyekt 957 Kedr which never left the design phase.  The Yasen is intended to replace Soviet-era SSNs and SSGNs, but Bogdanov thinks it’s too complex and expensive to be built in the numbers Russia may need.  Twenty years ago the Russian Navy was planning for not less than 30 [sized of course against the U.S. fleet], and currently it has not more than 30 SSNs and SSGNs, and this is considered insufficient. 

Despite the uncertainty above, Bogdanov says one still hears talk about the need to develop a fifth generation submarine, but it’s unknown if there will be any development work on one.
 

GOZ War Winding Down?

Vedomosti’s Aleksey Nikolskiy sees a possible end to the conflict between the Defense Ministry and industry over the production of strategic nuclear systems.  His OSK source claims a multiyear Defense Ministry contract with Sevmash for proyekt 955 Borey-class SSBNs will be concluded in the coming week.  This would reportedly leave OSK with just one contract remaining to be completed.

Conclusion of a 40-billion-ruble contract for three proyekt 11356M frigates was announced Wednesday.

Vedomosti’s source said the Defense Ministry and OSK also finished a deal for proyekt 885 Yasen-class SSNs several days ago.  The paper once again cites Konstantin Makiyenko’s 500 billion ruble price tag for the new SSBNs and SSNs.

An industry source tells Vedomosti that all MIT’s ballistic missile contracts are complete.

While deals for renovating Russia’s strategic forces are apparently done at last, not all contracts for conventional armaments are finished, particularly those involving Rostekhnologii and its enterprises, according to the director of one of them.

What’s this mean?

The conclusion of submarine / SLBM / ICBM production contracts would be a relief to both sides since their absence has been the biggest GOZ news story.  If all this is done, or almost done, one would expect a major government or Defense Ministry press announcement soon.

If the submarine deals are worth 500 billion rubles, that is, once again, apparently closer to Defense Minister Serdyukov’s price than to OSK’s.

The proyekt 11356M frigates are updated Krivaks (or Talwars for India), and they aren’t exactly cheap.

The issue of incomplete contracts with Rostekhnologii’s enterprises is significant given the size and breadth of their work on weapons and military equipment.  People will ask which enterprises and systems are in question.  It also contradicts Serdyukov’s recent claims that only OSK deals needed to be inked, and implies there are lingering problems and issues in areas other than shipbuilding.

The GOZ Last Week (Part I)

Let’s start with the news.  In short, Defense Minister Serdyukov told the press all GOZ-2011 contracts, except ones with OSK, were signed.  But most news outlets concluded he failed to meet Prime Minister Putin’s August 31 deadline for finishing the contracting process.

ITAR-TASS reported the Defense Ministry signed its fourth contract with OSK on August 29.  It was with Baltic Shipbuilding Factory “Yantar” for three Proyekt 11356M frigates.  Kommersant reported others are with Admiralty for three Proyekt 636 diesel-electric submarines and with Zvezda Shipyard in the Far East for nuclear submarine (probably OSCAR II-class) repairs and modernization.

But the largest and most important contracts with Sevmash for Proyekt 955 Borey-class SSBN and Proyekt 885 Yasen-class SSN production are still not signed.  The contract is supposed to cover two of the former and one of the latter that are already (or almost) complete.  Kommersant says the contracting delay means a fourth 955 and second 885 won’t be laid down until sometime in 2012.

ITAR-TASS concluded there are still differences over pricing although there is progress in the negotiations.  The wire service writes that Sevmash refuses to make concessions taking below a minimum profitability level, while the Defense Ministry calls price increases unjustifiable, and says it will only pay for concrete items regardless of the producer’s profitability.

On September 1, ITAR-TASS reported Serdyukov’s announcement that, on the whole, the Prime Minister’s order to conclude all GOZ contracts had been fulfilled.  It provided some choppy, weaseling quotes from Serdyukov:

“We are reprogramming for other requirements – precision weapons mainly, aviation, air defense . . . some suppliers because of some obstacles can’t provide their products.  . . . now we’re making changes – on the order of 30 billion [rubles].  . . . in essence, this is a formality  . . . .  Essentially, we’ve been through the entire agreed part.  The signing itself occurred yesterday-day before yesterday.  Only the United Shipbuilding Corporation contract remains.  Perhaps that’s all.”

Kommersant added Serdyukov’s comment that:

“We, unfortunately, can’t accept the figures which industry gives us.  For the most part, they are simply unjustified.”

Kommersant’s sources maintain, in addition to OSK, contracting with OAK and MIT remains incomplete, and no one’s willing to guess when this still-difficult process will end.

On September 2, Kommersant’s source said part of MIT’s contracts are done, but it would be premature to say the process is complete.

ITAR-TASS added that Sevmash’s contract is now supposed to be signed in mid-September.  The factory reportedly will agree to current prices for its submarines in exchange for some kind of “coefficient” to offset their rising costs starting in 2013.  The wire service also claimed there are now 6 of 13 OSK contracts signed.  And it put the cost of a Borey-class SSBN at a somewhat hard-to-believe 23 billion rubles.  OAK and MIT sources also told ITAR-TASS their contracts aren’t complete.

Vedomosti cited Konstantin Makiyenko on long-term submarine production costing 500 billion rubles.  If that’s eight Borey- and eight Yasen-class boats, it’s a $17 billion contract, basically $1 billion per submarine.  Thirty billion rubles a boat is a lot closer to 23 billion than the 47 or 112 billion that Serdyukov complained about in July.

Despite indications to the contrary, one has to wonder if Serdyukov isn’t very slowly winning his battle with the OPK.  But ultimately, it’s hard to say before we see what gets delivered, when, and how good it is.

Navy Day

Sankt-Peterburg Submarine in the Bolshaya Neva (photo: www.flot.com)

In honor of Navy Day — the 315th anniversary of the Russian Navy’s establishment – here are this week’s sound bites from Navy CINC, Admiral Vladimir Vysotskiy.  RIA Novosti will publish a complete interview with him tomorrow.

Vysotskiy says the Navy expects “not less than eight” proyekt 885 SSNs by 2020.  Some sources maintain the number is six.

Unit 1 Severodvinsk is preparing for sea trials in August, and unit 2 Kazan is expected by 2015.  They’ll have to pick up the pace to get eight by 2020.

Vysotskiy says work on a new destroyer will begin in 2012, and be completed in 2016.  This is the one he suggested might be nuclear-powered.

The CINC’s other comments covered the Black Sea Fleet. 

He claimed the BSF will get six proyekt 636 diesel-electric submarines in the coming years.  Its sole submarine now, proyekt 877 Varshavyanka-class SS Alrosa is currently in the Baltic for repair.

RIA Novosti recalled Vysotskiy’s past comments about obtaining 15 frigates and diesel submarines for the BSF by 2020 in a 60-30 proportion.  He also said a frigate and submarine were specifically laid down for the BSF in 2010, and would be every year henceforth.  He claimed the fleet would be renewed by 2020 through new construction rather than inter-fleet transfers.

Moskovskiy komsomolets and Newsru.com reported on the BSF’s drastic ten-fold decline since 1997.

This week TsAMTO cited a Baltic Fleet press release saying it expects to get the Neustrashimyy-class FF Yaroslav Mudryy, proyekt 20380 Steregushchiy-class FFLs Steregushchiy, Soobrazitelnyy, and Boykiy, proyekt 677 Lada-class SS Sankt-Peterburg, as well as assault ships and other craft.  The BSF may be expecting to get some of these ships as well.

Severodvinsk Trials and GOZ Tribulations

Severodvinsk (photo: RIA Novosti / Vladimir Rodionov)

Your typical good news, bad news story . . . happily for the Russian Navy, the Severodvinsk is nearing its first at-sea testing, but the new submarine has also been held up as a prime example of outrageous price increases in this year’s state defense order.  Final delivery of this SSN, as well as the first two Borey-class SSBNs, represents a big part of troubled GOZ-2011.

RIA Novosti reports new fourth generation Yasen-class (proyekt 885) SSN Severodvinsk will soon head into the White Sea for two months of underway testing, according to Malakhit Design Bureau General Director Vladimir Pyalov.  He added that, after this at-sea period, the final phase of state testing will take place.  

A very precise Mr. Pyalov says Severodvinsk is currently 98.9 percent complete.  He thinks the Navy will accept the new boat before year’s end and, in all, six of these multipurpose submarines will be built.  The second proyekt 885 Kazan is slated for delivery in 2015. 

RIA Novosti says proyekt 885 is a double-hulled, single-shaft boat with a reduced acoustic signature.  The conning tower has a streamlined, oval shape.  The boat is divided into ten compartments. 

For the first time, according to RIA Novosti, Russian designers put the submarine’s torpedo tubes amidships to allow for a new bow-mounted sonar system.  Proyekt 885 has eight vertical launch tubes for supersonic cruise missiles.  It has new communications and navigation systems as well as a fundamentally new nuclear power plant, according to the news agency’s report.  The new submarine is said to be first in noise reduction and stealth among attack submarines worldwide.

But the Severodvinsk couldn’t evade detection in the furor over breakdowns in the state defense order.

Earlier this month, RIA Novosti reported on disputes between the United Shipbuilding Corporation (OSK), submarine-builder Sevmash, and the Defense Ministry over naval construction in this year’s GOZ.  In particular, the military accuses the builder of doubling its prices for proyekt 955 Yuriy Dolgorukiy and proyekt 885 Severodvinsk.

An OSK spokesman defended Sevmash saying the cost of its work on Severodvinsk is only 30 percent of the total price, with the balance being the cost of armaments and components supplied by several dozen enterprises.  He blamed inflation in the industrial sector and the economy more generally.

Summarizing his discussion of submarines with OSK, RIA Novosti reports, Defense Minister Serdyukov said:

“They are giving us an increase in prices on new orders, and, naturally, we don’t agree with this.”

But, he added he’s convinced the Defense Ministry will persuade the producer to lower its prices.

Izvestiya mentioned that Severodvinsk was originally intended for a production run of 30 submarines, now reduced to six more than 20 years later.  As recently as March, the Navy still publicly hoped for ten.

Serdyukov told the paper:

“. . . it’s incomprehensible what the price of the ship [sic] consists of, if the cost of the lead boat was 47 billion rubles ($1.7 billion), but the next, exactly the same is now 112 billion ($4 billion).”

“Of course, the price will grow if, in the cost of one ship [sic], they include all accompanying expenditures on other enterprise projects in no way connected with it, like maintaining kindergartens, infrastructure, etc.”

“We’re prepared to pay, but on the condition that the price formation process will be transparent.  As practice shows, if all articles in the contracts are “decoded,” then it seems it’s possible with confidence to deduct up to 30% from the final cost of a finished product.”

These must be bitter words for an enterprise that went many, many years without completing its trademark product — a nuclear-powered submarine.

A Sevmash source says the cost of submarine construction is directly related to higher prices for materials, energy, and integration:

“The entire range of equipment for a submarine is supplied by monopolistic companies trying to dictate their prices.”

Dolgorukiy, Bulava, Severodvinsk

Submarine-related news notes . . .

Russian press services have announced that the state commission on the Bulava has finished analyzing the results of the last two launches.  The next test will be in the second half of December, and the exact date will depend on White Sea weather conditions.

It’s pretty, but not absolutely, certain that new Borey-class SSBN Yuriy Dolgorukiy will be the launch platform.  The final decision on this will be made in the first ten days of December.  One supposes another shot from Dmitriy Donskoy remains a remote possibility.

If the pending launch is a success, the next phase of testing will begin in May 2011.

Regarding fourth generation (proyekt 885, Yasen) SSN Severodvinsk, the boat is still fitting out, and the Navy expects it to join the fleet in 2011.  Like DolgorukiySeverodvinsk was under construction for many years.  ITAR-TASS said this morning 6 of these submarines are now planned.